The Project Plan and Timeline
On this page
In this lesson, you will learn:
- How to build a week-by-week plan
- Why dependencies drive the timeline
- The Clear View 12-week plan
🔁 Quick look back: Last time: Roles and Responsibilities (RACI). You learned how a RACI shows who does what.
1 The Problem: Twelve Weeks Go Fast
Twelve weeks sounds like a lot. But one late item can push everything:
- Scans can’t start without MID Server hosts.
- Hosts can’t be used without firewall rules.
- Firewall rules need a change approval.
👉 The fix: Build the plan backwards from the gates, and start slow items first.

2 Building the plan
- Start from the gates and their dates.
- List the work each gate needs.
- Mark dependencies: what must finish first.
- Put slow items early, such as firewall changes.
- Add who is needed each week.
Key term: Dependency
Work that can’t start until other work is done.
Key term: Critical path
The chain of work that decides the end date. A delay here delays everything.
3 The Discovery critical path
On most Discovery projects, the critical path runs through the client’s prerequisites.
- MID Server hosts → firewall rules → service accounts → readiness check → first scan.
⚠️ Heads up: If a firewall change needs CAB approval, add those weeks to the plan from day one.
4 Project Clear View: How We Implemented It
📍 Situation: The SOW gives 12 weeks. SNWR’s firewall changes take about three weeks.
🧭 Decision: Plan backwards from the gates, and start prerequisite requests in week 2.
🛠️ Steps we took:
- Placed the six gates on the calendar.
- Listed the work behind each gate.
- Marked the critical path: hosts, firewall rules, accounts, readiness check.
- Scheduled prerequisite requests for week 2, overlapping design.
✅ What we verified:
- Hana and Anita accepted the dates.
- Ravi confirmed the firewall timing fits week 5.
📁 Evidence: The Clear View plan, version 1, shared after kickoff.
5 Quick recap
- Plan backwards from the gates.
- A dependency is work that must wait for other work.
- The critical path decides the end date.
- In Discovery, prerequisites are usually on the critical path.
6 Check yourself
Think of your answer first. Then tap to check.
1 What is the critical path? Show answer
The chain of work that decides the end date. A delay there delays the whole project.
2 Why start prerequisite requests in week 2? Show answer
They take weeks, and scans can’t start without them.
3 What’s usually on a Discovery project’s critical path? Show answer
Hosts, firewall rules, accounts and the readiness check.
Nice work! Clear View has a realistic plan. 🎉
Next up: Risks, Assumptions and Dependencies