The Prerequisites Checklist

4 min read
On this page

In this lesson, you will learn:

  • What a client must provide before scanning
  • Why prerequisites cause most delays
  • SNWR’s 14 items

πŸ” Quick look back: Last time: The Design Review and Sign-Off. You learned how SNWR reviewed and signed the design at gate 2.

1 The Problem: Prerequisites Take Longer Than the Build

The build itself takes days. But before it can start, SNWR must provide hosts, network access and accounts. Each one needs a different team:

  • Priya builds hosts.
  • Ravi opens firewalls, through CAB.
  • Farah approves everything.

🎯 The problem: Prerequisites take longer than the build itself.

πŸ‘‰ The fix: List every prerequisite, give each an owner and a date, and start them early.

Table of prerequisite groups, count and owner.
Figure 1. The Clear View prerequisites checklist.

2 Common Discovery prerequisites

  • MID Server hosts, with the right OS and size.
  • Firewall rules from each MID Server to its targets.
  • Outbound HTTPS from MID Servers to the instance.
  • Service accounts with the right rights.
  • Security approval.
  • A change for the first scans.

3 Managing them

  1. Give each item an ID, owner and due date.
  2. Send each request in writing, with exact details.
  3. Track status every day.
  4. Validate each item when it’s delivered. Don’t just tick it.

⚠️ Heads up: ‘Done’ from the client isn’t the same as ‘working’. Test each item yourself.

4 Project Clear View: How We Implemented It

πŸ“ Situation: Design is nearly signed. Scans need to start in week 6.

🧭 Decision: Build the checklist in week 2, and send every request that week.

πŸ› οΈ Steps we took:

  1. Listed 14 items, PR-01 to PR-14.
  2. Gave each an owner and a due date before week 5.
  3. Sent the requests in writing.
  4. Set up a daily 10-minute check with Hana.

βœ… What we verified:

  • Every item has an owner and a date.
  • All requests were sent by the end of week 2.

πŸ“ Evidence: The prerequisites tracker, PR-01 to PR-14.

5 Quick recap

  • Prerequisites usually take longer than the build.
  • Give each item an ID, owner and date.
  • Send exact requests in writing.
  • Test each item when it’s delivered.

6 Check yourself

Think of your answer first. Then tap to check.

1 Why start prerequisites early? Show answer

They involve other teams and approvals, so they take weeks.

2 What’s the difference between ‘done’ and ‘working’? Show answer

The client may say it’s done, but you must test that it really works.

3 How many prerequisite items does Clear View have? Show answer

Fourteen.

Nice work! Clear View’s prerequisites are requested. πŸŽ‰